Guide to Connecting to the Medium-Voltage Grid

Connecting a facility to the medium-voltage grid is a procedure with clearly defined steps, but there are also enough points where a project can lose several months if those steps are carried out in the wrong order.
This guide explains how the process works in practice, from the initial concept to energising the transformer substation.


The process begins with an application to the distribution system operator, defining the location, requested capacity and intended use of the facility.


The operator then issues the grid connection conditions, specifying the connection point, connection method, technical equipment requirements and the investor’s obligations. For higher capacities and connections involving electricity generation, additional grid impact studies may also be required.


These conditions form the basis for everything that follows. The application should therefore be submitted early and with a realistic capacity estimate, because changing the requested capacity at a later stage may mean returning to the beginning of the process.


Based on the connection conditions, the design documentation for the transformer substation and the connection line is prepared and submitted through the required approval procedure.
Two common mistakes are made at this stage.


The first is sizing the system only according to current electricity consumption, without allowing sufficient reserve for future growth, solar generation or EV chargers, even though the additional cost of selecting equipment one capacity step higher is often relatively small.


The second is designing equipment that formally meets the minimum requirements but does not reflect the facility’s actual needs in terms of reliability, monitoring and future expansion.
The next step is signing an agreement with the distribution system operator, which defines the connection fee, scope of works and project deadlines.


Part of the works is carried out by the operator, while the remainder is performed by the investor through contractors holding the appropriate licences.


At the same time, construction of the transformer substation proceeds, including civil works, equipment installation, cable connections and grounding.


Effective coordination between these two workstreams is where several weeks can be saved. A completed substation waiting for the connection line, or a completed line waiting for the substation, means that someone is paying financing costs for equipment that is not yet operational.

Before energisation, all required testing must be completed. This includes grounding resistance measurements, cable insulation testing, protection system functionality checks and verification of metering equipment.
The operator inspects the completed installation and, once everything complies with the connection conditions and approved design, the substation is energised and the agreements for system access and electricity supply are signed.


The administrative work at this stage may appear to be a formality, but this is where many delays occur when project documentation has not been maintained properly throughout construction.
The overall duration depends on the complexity of the connection, equipment delivery times and the operator’s schedule. However, for a serious industrial connection, the realistic timeframe should be measured in months rather than weeks.


The single most important factor in accelerating the process is complete and accurate documentation at every stage.


The most common cause of delay is the optimistic assumption that one of the steps will be completed faster than the formal procedure allows.


An experienced partner that has completed this process many times does not primarily create savings through a lower equipment price, but by reducing delays. In grid connection projects, time is usually the most expensive item.

How to Reduce Peak Demand With Battery Storage

Learn how to reduce peak demand with battery storage, analyze energy consumption, and size a BESS for lower costs and reliable facility operation.

Guide to Factory Energy Audits and Lower Energy Costs

A Guide to Factory Energy Audits Shows Where a Facility Is Losing Energy, What to Measure, and How to Select Measures With a Clear Return on Investment and Lower Risk.

When Do Photovoltaic Systems for Businesses Pay Off?

Photovoltaic Systems for Businesses Reduce Energy Costs and Operational Risk. Learn How to Size a Solar Power Plant Based on Energy Consumption and Operating Profile.

Guide to EPC Contracts for Project Delivery

Guide to EPC Contracts: How to Define Scope, Timelines, Warranties, and Risks for the Successful Delivery of Solar and Energy Projects in Serbia Today.

How Much Does an Industrial UPS Cost in Serbia?

How Much Does an Industrial UPS Cost in Serbia? Learn What Determines the Investment Cost, How TCO Is Calculated, and What Should Be Included in the System Specification for an Industrial Facility.

Best Peak Shaving Solutions for Industry

The Best Peak Shaving Solutions Reduce Peak Demand, Electricity Costs, and Downtime Risk. Learn How to Accurately Size BESS, Solar, and Load Management Systems.

Guide to Powering Critical Infrastructure

Guide to Powering Critical Infrastructure: How to Design UPS Systems, Generators, Batteries, and BESS for Operational Continuity, Risk Management, and the TCO of Every Investment.

Lithium vs. Lead-Acid Batteries in Practice

Lithium vs. Lead-Acid Batteries: Compare Lifespan, Safety, Cost, and TCO for UPS, Solar Systems, and Critical Industrial Loads.

Learn more

Enter your information to receive more information on the selected topic

Planiraj svoju elektranu

Odgovorite na pitanja ispod kako bi naš inženjerski tim mogao da uradi studiju izvodljivosti nakon koje će vas kontaktirati.

Nakon dostavljanja podataka, naš stručni tim će analizirati Vaš zahtev i pripremiti personalizovanu ponudu sa predlogom optimalnog solarnog sistema za Vaš objekat. Kontaktiraćemo Vas kako bismo predstavili predloženo tehničko rešenje, očekivanu proizvodnju električne energije i odgovorili na sva Vaša pitanja u vezi sa realizacijom projekta.

Solarna elektrana omogućava dugoročno smanjenje troškova električne energije, veću energetsku nezavisnost domaćinstva i doprinosi očuvanju životne sredine korišćenjem energije iz obnovljivih izvora.

Planiraj svoju elektranu

Odgovorite na pitanja ispod kako bi naš inženjerski tim mogao da uradi studiju izvodljivosti nakon koje će vas kontaktirati.

Nakon dostavljenih podataka za izradu studije izvodljivosti, i kada naš inženjerski tim uradi studiju izvodljivosti, predlažemo da organizujemo sastanak gde bismo Vam prezentovali studiju. Takođe, tom prilikom ćemo detaljnije pričati o samoj investiciji i benefitima ulaganja u obnovljive izvore energije, kao i o mogćim otpisima putem dostupnih fondova (IPARD, RAS, EBRD).  

Pored uštede električne energije, solarnom elektranom možete generisati i dodatne benefite kao što su direktran uticaj na smanjenje emsije CO2 što može direktno uticati na konkurentnost prilikom izvoza na tržištu EU, kao i dodatne benefite uštede hlađenja.

Planiraj svoju elektranu

Izaberite tip objekta za koji želite da planirate solarnu elektranu