A Transformer Substation for a Solar Power Plant Is Not the Same as One Designed for Consumption

At first glance, a transformer substation is simply a transformer substation: a transformer, medium-voltage switchgear and distribution equipment.

However, a substation that supplies a factory and one that delivers electricity from a solar power plant to the grid perform two different functions. The differences in their design are significant enough for an incorrect assumption to become expensive.

In a conventional consumer substation, electricity flows from the grid towards the loads, and all equipment, protection systems and metering are configured for that direction of power flow.

In a solar power plant, the transformer operates as a step-up transformer and electricity flows from the plant towards the grid. At facilities that also have their own electricity consumption, the direction of power flow can change throughout the day: electricity is imported in the morning and exported around midday.

The equipment must therefore be selected and configured for power flow in both directions, while the metering system must distinguish between electricity imported from and exported to the grid.

A consumer substation is sized according to the consumer’s peak load.

A solar power plant substation is sized according to the plant’s rated output, which may remain at full power for several hours on a clear day, day after day, throughout the production season.

This is a more demanding thermal operating profile than typical electricity consumption with short peaks, so the transformer must be selected without optimistic assumptions regarding spare capacity.

Another important consideration is low-load operation at night. When the solar power plant is not producing electricity, the transformer remains energised and continues to generate no-load losses, which must be included in the project’s financial model.

A grid-connected power plant is not a passive network user.

Through the grid connection conditions, the distribution system operator defines how the plant must behave, including protection settings at the point of connection, operating requirements during grid disturbances and, where required, participation in reactive power control.

Compliance with these settings must be demonstrated during commissioning, and the relevant documentation is required before the plant can be connected to the grid.

This additional layer of requirements is largely absent in a conventional consumer substation. It is also where the difference is most evident between a contractor experienced in power generation projects and one that has worked only on traditional transformer substations.

The most common industrial application today is a combined system: an existing facility installs a solar power plant, so the same substation both supplies the facility and exports surplus electricity to the grid.

In this case, it is necessary to verify whether the existing transformer and medium-voltage switchgear can withstand the new operating regime, whether the protection and metering systems support power flow in both directions and whether sufficient grid connection capacity is available for electricity export.

Sometimes the solution requires only a minor modification. In other cases, an additional switchgear cell or a higher-capacity transformer may be required.

The important point is that this assessment must be completed during the solar power plant design stage, rather than becoming an unexpected issue during the technical inspection.

That is the difference between a planned budget item and a delay affecting the entire project.

What Happens When a Transformer Fails?

Transformer failure is not something companies like to think about because it is relatively rare.

Transformer Substation Maintenance: What, How Often and Who Is Qualified to Perform It

A transformer substation is a piece of equipment that rewards routine.

One Large Transformer or Two Smaller Ones

When designing a transformer substation for a larger industrial facility, a question eventually arises that may seem like a minor detail but actually determines the facility’s reliability for the next thirty years: should the system use one transformer with the full required capacity, or two smaller transformers that provide the same combined capacity?

Transformer Losses: A Cost That Runs 24 Hours a Day

A transformer is one of the most efficient machines ever created, with an efficiency that exceeds 98 percent.

Guide to Connecting to the Medium-Voltage Grid

Connecting a facility to the medium-voltage grid is a procedure with clearly defined steps, but there are also enough points where a project can lose several months if those steps are carried out in the wrong order.

Dry-Type or Oil-Immersed Transformer

When selecting a power transformer, one question arises in almost every project: dry-type or oil-immersed?

Your Own Transformer Substation or a Connection Through a Third-Party Substation

Many companies operate for years connected to the low-voltage network through a distribution transformer substation. They only begin considering their own substation when the distribution system operator informs them that no additional capacity is available for a planned expansion.

Transitioning the Grid from 10 kV to 20 kV: What It Means for Your Equipment

For decades, Serbia’s distribution network has operated with two medium-voltage levels: 10 kV and 20 kV.

Learn more

Enter your information to receive more information on the selected topic

Planiraj svoju elektranu

Odgovorite na pitanja ispod kako bi naš inženjerski tim mogao da uradi studiju izvodljivosti nakon koje će vas kontaktirati.

Nakon dostavljanja podataka, naš stručni tim će analizirati Vaš zahtev i pripremiti personalizovanu ponudu sa predlogom optimalnog solarnog sistema za Vaš objekat. Kontaktiraćemo Vas kako bismo predstavili predloženo tehničko rešenje, očekivanu proizvodnju električne energije i odgovorili na sva Vaša pitanja u vezi sa realizacijom projekta.

Solarna elektrana omogućava dugoročno smanjenje troškova električne energije, veću energetsku nezavisnost domaćinstva i doprinosi očuvanju životne sredine korišćenjem energije iz obnovljivih izvora.

Planiraj svoju elektranu

Odgovorite na pitanja ispod kako bi naš inženjerski tim mogao da uradi studiju izvodljivosti nakon koje će vas kontaktirati.

Nakon dostavljenih podataka za izradu studije izvodljivosti, i kada naš inženjerski tim uradi studiju izvodljivosti, predlažemo da organizujemo sastanak gde bismo Vam prezentovali studiju. Takođe, tom prilikom ćemo detaljnije pričati o samoj investiciji i benefitima ulaganja u obnovljive izvore energije, kao i o mogćim otpisima putem dostupnih fondova (IPARD, RAS, EBRD).  

Pored uštede električne energije, solarnom elektranom možete generisati i dodatne benefite kao što su direktran uticaj na smanjenje emsije CO2 što može direktno uticati na konkurentnost prilikom izvoza na tržištu EU, kao i dodatne benefite uštede hlađenja.

Planiraj svoju elektranu

Izaberite tip objekta za koji želite da planirate solarnu elektranu